The following report was prepared by the
Architect and will be assumed to be correct unless written exceptions are
received within two weeks of publication date.
Meeting Date: 27 March
2001
Report Date: 3
April 2001
Location: Henry
Wells Room, Long Library, Wells College
Project No: 00068
Subject: Science
Building design kickoff meeting
Attendees:
Wells College Tom
Vawtner
Niamh
O’Leary
Chris
Bailey
Candace
Collmer
Harriet
Barone
Jay
Woolford
Ellen
Hall
Jay
Woolford
HOLT Architect, P.C.
Graham
Gillespie
Grace
Chiang
Discussion:
1.
Introduction of the project team
a.
HOLT
:
i.
Grace Chiang
ii.
Graham Gillespie
b.
M/E
Engineering from Rochester, New York will be designing the mechanical and
electrical engineering systems.
Unfortunately, Charlie Wilson who has been involved with us to date is
too busy to stay on as part of the team.
c.
HOLT
will also be bringing in other consultants who will be involved with the structural
system design, acoustical and A/V systems, landscape architecture and civil
engineering. These consultants will not
all be involved in the charrettes but as the project progresses some of these
specialty resources may join some us from time to time.
d.
Ellen
Hall will be leading the effort to ensure that the building meets the college’s
long-term academic goals and mission.
e.
Diane
Hutchinson will be involved in making sure the building develops within the
financial budgets that have been established, and the planning and construction
schedules for the college administration.
f.
Jay
Woolford will be assisting the college in securing the funding for the project
and assisting the college with project management.
g.
The
college will retain a Construction Manager/Contractor within the next month to
assist with planning for construction, budgeting and pricing, and establishing
construction schedules.
2.
The
schedule that we are striving to achieve is as follows:
a.
Complete
schematic design by early summer, in approximately 3 months.
b.
Complete
design development by late summer, in approximately 3 months.
c.
Complete
Construction Documents around the end of 2001, in approximately 4 months.
3.
It
is desirable to initially meet as a whole group, later breaking down into
smaller groups to discuss detailed needs for each space.
a.
During
schematic design the building footprint will be established, building plans
will be worked out and three-dimensional development of the building will be
determined. General principles about
the arrangement of each space will be affirmed.
b.
During
design development detailed development of the spaces will be worked out. For example exact cabinet details, outlet
locations, and finishes would be discussed during this phase.
c.
Construction
documents, drawings and specifications, are then prepared to represent the work
to date for the CM/contractor to construct the building.
4.
Would
like to meet weekly, mostly as a group for the remainder of this semester as
schematic design is developed. Given the stated schedule it is important that
we have the opportunity to meet during the summer, which is when most of design
development will be completed. At this
time the thought is that 2-4 four meetings over the course of the summer might
satisfy this need. This will need to
be reassessed as the time gets closer and we know how much has been
accomplished during the rest of this semester.
5.
Review
of the revised program dated 15 April 2000.
This material was distributed to the faculty for review prior to this
meeting. The following comments and
discussion ensued:
a.
It
was noted that a layout for Lab Type C is missing from the report. Grace responded that Lab Type C was not
deemed to be a desirable layout during the review of Lab Types and so it was
excluded from the final report.
b.
In
the Classroom Needs Analysis section of the report Spring Semester 1999 is
included twice. Grace will review which
semesters were analyzed, and replace with missing information at the next
meeting if required.
6.
Lecture
hall and classrooms: Ellen pointed out
that the site selected for the science building is very central relative to the
other college academic facilities, therefore, an argument for including general
teaching spaces for use by the entire college in this new building may be logical. Jay indicated that the square footage for
these spaces have in fact been included in the budget. It was further clarified that the lecture
hall should be a dedicated lecture hall and not try to serve too many purposes
(e.g., it should not also be a concert hall, performing space). The design will move forward with the
inclusion of these spaces.
7.
Offices:
the revised program on Page 8 indicates offices of 160 net square feet while
the larger diagrams on page 28 indicate 150.
HOLT confirmed that the 160 is included in the tabulated total square
footage numbers that have been used for budgeting.
a.
It
was noted that each faculty member at Wells may very well teach a wider range
of courses than faculty at a larger institution. This results in the need for keeping more course materials in
each person’s office. There was
continued discussion about the adequacy of the 160 net square foot office.
b.
Also
discussed whether one additional office is required for visiting faculty,
temporary faculty (e.g., sabbatical replacements), taking the total faculty
offices to eleven. In the end it seemed
that the one additional office currently included in the program is adequate,
so the total will be kept at ten. It
was noted than many of the existing offices in Zabriskie are +200 net
square feet. However, it was also noted
that in the new program, all research activities would be conducted in
dedicated research space and not in offices, while the current offices serve
both these functions.
8.
Lounge:
a.
Discussed
the possibility of dividing the 400 net square feet, which is allotted to
lounge space. It was agreed that this
might be desirable, perhaps having one lounge on each main floor level.
b.
Discussed
whether it is necessary to have a dedicated faculty/staff lounge. Consensus seems to be that this was probably
not required.
9.
Storage
and Prep rooms
a.
Some
concern was expressed about the size of prep and storage rooms. The number of rooms indicated in the revised
program may not be adequate. It was
agreed that the number of rooms could change by simply dividing up the total
square footage assigned to these areas differently. However, there was also concern that perhaps not enough total
space was allotted to this function.
Faculty will think in detail about equipment and materials that should
be located in these spaces and how these spaces will support the teaching and
research labs. (E.g., where will
teaching microscopes, laminar flow hood, incubator, etc. be located.) This discussion will continue at the next
meeting
10.
It
was questioned whether the number of labs programmed would be able to support
the course schedule. HOLT suggested
that a mock-up schedule be run. It was
agreed that this would be an important issue to confirm. Ellen and the faculty will pursue.
11.
Chris
B. noted that he was planning on holding some of the small upper-level
specialized chemistry courses in the research lab.
12.
The
next meeting is scheduled for Thursday April 5, 2001 at 4:30 PM. At that time we will try to conclude the
confirmation and review of the functional space program and concurrently begin
discussion about space relationships and proximities. HOLT will bring some bubble diagrams outlining possible space
relationships to assist this dialogue.
Prepared
by,
HOLT ARCHITECTS, P.C.
Grace
Chiang, AIA
Vice
President
Cc: Attendees, L. Ryerson, D. Hutchinson, A. Bellinzoni, M. Flowers, S. Heinekamp, L Schwab, C. Wahl
This page belongs to Dean Ellen Hall. Please see our statement of responsibility.